Mechanical Design and Project Planning Process Chart

Project Manager: Zafar Samandarov | 2025
Project Code: NOV-MIRJK-2025
Project Name: MIR JK Mechanical Design Project
Project Manager: Zafar Samandarov
Project Acquisition
Customer contract and project approval
Mechanical Calculations
Static and dynamic analysis
Design Phase
3D modeling and CAD drawings
Sheet Preparation
Preparation of technical drawings
Approval and Delivery
Customer approval and project delivery

Current Stage

Design Phase

3D modeling and detailed design work continues

Timeline

March 15, 2025
Project Start Date
September 30, 2025
Planned Completion
98 days
Remaining Time
Project Progress 45%

Project Team

Zafar Samandarov
Project Manager
Ahmet Yılmaz
Mechanical Designer
Mehmet Kaya
Manufacturing Engineer
Ayşe Demir
Quality Control